XYZ CONSTRUCTION COMPANY | |||||
LOCATION | |||||
ROAD RECONSTRUCTION ESTIMATE | |||||
ROAD: | ZONE: | ||||
LENGTH: | WIDTH: | AREA: | |||
ITEM | DESCRIPTION | QTY | UNIT | RATE | AMOUNT |
BILL NO. 1 | |||||
1 | PRELIMINARIES | ||||
1.1 | Provide, furnish and maintain one site office for the Project Engineer's Representatives | ||||
1.2 | Provide, Survey equipments, and assistance as may be required by the Project Engineer. | ||||
1.3 | Provide, furnish and maintain one site office for the Project Engineer's assistant staff | ||||
1.4 | Allow for the stationeries for the Engineer's staff | ||||
1.5 | Allow for the purchase of project vehicles | ||||
1.6 | Allow for the repair, running cost and maintenance of project vehicles | ||||
1.7 | Allow for the cost of progress photographs | ||||
1.8 | Allow soil investigation/laboratory testing of materials | ||||
1.9 | Allow for laboratory testing of materials | ||||
1.1O | Provide for compensation of economic crop, existing installation, demolition and other utilities | ||||
1.11 | Allow for services to project engineer's representative | ||||
1.12 | Allow for the construction and furnishing of a road camp in the area | ||||
1.13 | Allow for road diversion. | ||||
TOTAL BILL NO. 1 CARRIED TO SUMMARY | |||||
BILL NO. 2 EARTHWORKS | |||||
ITEM | DESCRIPTION | QTY | UNIT | RATE | AMOUNT |
2.1 | Clear site and dispose as directed | SM | |||
2.2 | Excavate any acceptable material except rock | ||||
2.3 | Excavate unsuitable materials and dispose | CM | |||
2.4 | Excavate top soil and dispose | SM | |||
2.5 | Replace item 2.3 with filling sand/laterite | CM | |||
2.6 | Replace item 2.4 with suitable filling material/Laterite | CM | |||
2.7 | Scarification of existing surface and cart away | M2 | |||
2.8 | Demolish existing obstructive structures and dispose off materials | PS | |||
2.9 | Reconstruct demolised fences that have '' Approved Building plan | ||||
TOTAL BILL NO. 2 CARRIED TO SUMMARY | |||||
BILL NO. 3 CULVERTS AND DRAINS | |||||
ITEM | DESCRIPTION | QTY. | UNIT | RATE | AMOUNT |
3.1 | Clearing of existing drainage facilities | LM | |||
3.2 | Demolition of existing culverts | LM | |||
3.3 | Demolition of existing inadequate drains and cart away. | LM | |||
3.4 | Provide and construct 1.00 X 1.00m drain to specification (with cover to serve as walkway) | LM | |||
3.5 | Provide and construct 1.00m X 1.00m Box Culvert to specification | LM | |||
3.6 | Provide and Construct Type 4A(1.0x 1.0m) drain Box culvert to specification | LM | |||
3.7 | Provide and construct 1.0mx 1.0m Box culvert to specification | LM | |||
3.8 | Provisions and construct 1.50m x 1.50m cross culvert to specification | LM | |||
3.9 | provide and construct (1.00x 1.00)m drain (Type 4A) to specification (outfall) | LM | |||
3.1O | Provision of walkway (1.2m) | LM | |||
3.1 | provide 200x500mm walls to adjoining roads | LM | |||
TOTAL BILL NO. 3 CARRIED TO SUMMARY | |||||
BILL NO. 4 PAVEMENT AND SURFACING | |||||
ITEM | DESCRIPTION | QTY. | UNIT | RATE | AMOUNT |
4.1 | Provide spread, shape and compact to 100% West African Standard Compaction naturally occurring materials as sub base not exceeding a compacted layer of 150mm / 225mm thickness | CM | |||
4.2 | Provide spread, shape and compact crushed stones as base course to a compacted thickness of 150mm. | ||||
4.3 | Provide spread, and compact 150mm all-in-aggregate as base course material | SM | |||
4.4 | Soil/Cement Stabilization | ||||
4.5 | Provide concrete kerb (0.45 X 0.15) including hauling as directed | LM | |||
4.6 | Provide and construct (1 x 1.5m) concrete walkway to specification | ||||
4.7 | Grade, wet and roll final base 3(times) | SM | |||
4.8 | Provide, lay and compact asphaltic concrete course to a compact thickness of 50mm including tack coat/prime coat (Binder) | SM | |||
4.9 | ……………..wearing course to a compact thickness of 25mm including tack coat/ prime coat | SM | |||
4.1O | Provide, lay on sharp sand bed 80mm thick interlocking stones, blind and compact | ||||
4.11 | Provide, lay on sharp sand bed 50mm thick interlocking stones, blind and compact for walkway | ||||
4.12 | Provide and spread sand to fill inter on paving stone | ||||
TOTAL BILL NO. 4 CARRIED TO SUMMARY | |||||
BILL NO. 5 OTHER WORKS | |||||
ITEM | DESCRIPTION | QTY. | UNIT | RATE | AMOUNT |
5.1 | Allow for dewatering | DAYS | |||
5.2 | Allow for Lane Marking | LM | |||
5.3 | Provision of streetlight, generator plus transformer inclusive (optional) | PS | |||
5.4 | Allow for Kerb painting with thermoplastic paint | SM | |||
5.5 | Allow for surface dressing (2 coats) | ||||
5.6 | Provide service duct | LM | |||
5.7 | Relocation of services | P.S | |||
5.8 | Provision of boulders | ||||
5.9 | Cast - in - situ (Embarkment) | ||||
TOTAL BILL NO. 5 CARRIED TO SUMMARY | |||||
SUMMARY OF BILL OF QUANTITIES | |||||
BILL NO | DESCRIPTION | AMOUNT (N) | |||
1 | Preliminaries | ||||
2 | Earthworks | ||||
3 | Culverts and Drains | ||||
4 | Pavement and Surfacing | ||||
5 | Other Works | ||||
Total | |||||
Add Contingency 5% | |||||
Sub Total | |||||
Add 5% VAT | |||||
Grand Total | |||||
Monday, 8 February 2016
SAMPLE OF ROAD CONSRUCTION BEME
SAMPLE OF ROAD CONSTRUCTION BEME
XYZ CONSTRUCTION COMPANY | |||||
LOCATION | |||||
ROAD RECONSTRUCTION ESTIMATE | |||||
ROAD: | ZONE: | ||||
LENGTH: | WIDTH: | AREA: | |||
ITEM | DESCRIPTION | QTY | UNIT | RATE | AMOUNT |
BILL NO. 1 | |||||
1 | PRELIMINARIES | ||||
1.1 | Provide, furnish and maintain one site office for the Project Engineer's Representatives | ||||
1.2 | Provide, Survey equipments, and assistance as may be required by the Project Engineer. | ||||
1.3 | Provide, furnish and maintain one site office for the Project Engineer's assistant staff | ||||
1.4 | Allow for the stationeries for the Engineer's staff | ||||
1.5 | Allow for the purchase of project vehicles | ||||
1.6 | Allow for the repair, running cost and maintenance of project vehicles | ||||
1.7 | Allow for the cost of progress photographs | ||||
1.8 | Allow soil investigation/laboratory testing of materials | ||||
1.9 | Allow for laboratory testing of materials | ||||
1.1O | Provide for compensation of economic crop, existing installation, demolition and other utilities | ||||
1.11 | Allow for services to project engineer's representative | ||||
1.12 | Allow for the construction and furnishing of a road camp in the area | ||||
1.13 | Allow for road diversion. | ||||
TOTAL BILL NO. 1 CARRIED TO SUMMARY | |||||
BILL NO. 2 EARTHWORKS | |||||
ITEM | DESCRIPTION | QTY | UNIT | RATE | AMOUNT |
2.1 | Clear site and dispose as directed | SM | |||
2.2 | Excavate any acceptable material except rock | ||||
2.3 | Excavate unsuitable materials and dispose | CM | |||
2.4 | Excavate top soil and dispose | SM | |||
2.5 | Replace item 2.3 with filling sand/laterite | CM | |||
2.6 | Replace item 2.4 with suitable filling material/Laterite | CM | |||
2.7 | Scarification of existing surface and cart away | M2 | |||
2.8 | Demolish existing obstructive structures and dispose off materials | PS | |||
2.9 | Reconstruct demolised fences that have '' Approved Building plan | ||||
TOTAL BILL NO. 2 CARRIED TO SUMMARY | |||||
BILL NO. 3 CULVERTS AND DRAINS | |||||
ITEM | DESCRIPTION | QTY. | UNIT | RATE | AMOUNT |
3.1 | Clearing of existing drainage facilities | LM | |||
3.2 | Demolition of existing culverts | LM | |||
3.3 | Demolition of existing inadequate drains and cart away. | LM | |||
3.4 | Provide and construct 1.00 X 1.00m drain to specification (with cover to serve as walkway) | LM | |||
3.5 | Provide and construct 1.00m X 1.00m Box Culvert to specification | LM | |||
3.6 | Provide and Construct Type 4A(1.0x 1.0m) drain Box culvert to specification | LM | |||
3.7 | Provide and construct 1.0mx 1.0m Box culvert to specification | LM | |||
3.8 | Provisions and construct 1.50m x 1.50m cross culvert to specification | LM | |||
3.9 | provide and construct (1.00x 1.00)m drain (Type 4A) to specification (outfall) | LM | |||
3.1O | Provision of walkway (1.2m) | LM | |||
3.1 | provide 200x500mm walls to adjoining roads | LM | |||
TOTAL BILL NO. 3 CARRIED TO SUMMARY | |||||
BILL NO. 4 PAVEMENT AND SURFACING | |||||
ITEM | DESCRIPTION | QTY. | UNIT | RATE | AMOUNT |
4.1 | Provide spread, shape and compact to 100% West African Standard Compaction naturally occurring materials as sub base not exceeding a compacted layer of 150mm / 225mm thickness | CM | |||
4.2 | Provide spread, shape and compact crushed stones as base course to a compacted thickness of 150mm. | ||||
4.3 | Provide spread, and compact 150mm all-in-aggregate as base course material | SM | |||
4.4 | Soil/Cement Stabilization | ||||
4.5 | Provide concrete kerb (0.45 X 0.15) including hauling as directed | LM | |||
4.6 | Provide and construct (1 x 1.5m) concrete walkway to specification | ||||
4.7 | Grade, wet and roll final base 3(times) | SM | |||
4.8 | Provide, lay and compact asphaltic concrete course to a compact thickness of 50mm including tack coat/prime coat (Binder) | SM | |||
4.9 | ……………..wearing course to a compact thickness of 25mm including tack coat/ prime coat | SM | |||
4.1O | Provide, lay on sharp sand bed 80mm thick interlocking stones, blind and compact | ||||
4.11 | Provide, lay on sharp sand bed 50mm thick interlocking stones, blind and compact for walkway | ||||
4.12 | Provide and spread sand to fill inter on paving stone | ||||
TOTAL BILL NO. 4 CARRIED TO SUMMARY | |||||
BILL NO. 5 OTHER WORKS | |||||
ITEM | DESCRIPTION | QTY. | UNIT | RATE | AMOUNT |
5.1 | Allow for dewatering | DAYS | |||
5.2 | Allow for Lane Marking | LM | |||
5.3 | Provision of streetlight, generator plus transformer inclusive (optional) | PS | |||
5.4 | Allow for Kerb painting with thermoplastic paint | SM | |||
5.5 | Allow for surface dressing (2 coats) | ||||
5.6 | Provide service duct | LM | |||
5.7 | Relocation of services | P.S | |||
5.8 | Provision of boulders | ||||
5.9 | Cast - in - situ (Embarkment) | ||||
TOTAL BILL NO. 5 CARRIED TO SUMMARY | |||||
SUMMARY OF BILL OF QUANTITIES | |||||
BILL NO | DESCRIPTION | AMOUNT (N) | |||
1 | Preliminaries | ||||
2 | Earthworks | ||||
3 | Culverts and Drains | ||||
4 | Pavement and Surfacing | ||||
5 | Other Works | ||||
Total | |||||
Add Contingency 5% | |||||
Sub Total | |||||
Add 5% VAT | |||||
Grand Total | |||||